Project: Furnace off-gas system

Project

Furnace off-gas system

During the winter shutdown period of only 14 days, a filter plant including the E-scope was fully replaced, commissioned and successfully put into operation.

The filter plant is connected to various primary and secondary processes which are balanced by means of a mixing chamber.

Category

Specifications

Application Primary & Secondary dedusting
Start-up date 2017
Type of Filter MSF 2-10-8/9-3
Filter surface 2.600 m²
Gas flow 185.000 m³/hr
Design Temperature 150°C
Design Pressure -750 daPa

Impressions

Other projects in the same industry

175.000 m³/hr

During the shutdown of only 20 days, the existing filter was dismantled and the new stainless steel filter was fully constructed & successfully commissioned. It […]

550.000 m³/hr

A high-capacity tertiary filter plant to prevent diffuse emissions of lead particles. The filter plant has a modular design, making it suitable for very high […]

35.000 m³/hr

An ATEX filter has been installed in an explosive environment. The filter installation is engineered for a maximum overpressure of 400 mbar and is equipped […]