Project: ESP waste incineration

Project

ESP waste incineration

An electrostatic precipitator was upgraded to increase electrode spacing combined with installing 3-phase transformers and raise internal design temperatures to 450°C, by altering the material into 1.5415 (16MO3). The modernization improved collection efficiency and enhanced system robustness.

Category

Specifications

Application Waste Incineration
Start-up date 2021 and 2022
Type of Filter Rothemühle and Lurgi
Scope 2 lines revamp of field 1 and 2 and maintenance of field 3 and 4
Design Temperature 450°C
Revamp scope Expanding the collecting electrode (NE) distance from 300 to 400mm. Upgrading the design temperature of the internals to 450°C. Optimizing the collecting electrode (NE) and discharge electrode (SE) knock systems. Replacing the HV transformers with a 3-phase version.

Impressions

Other projects in the same industry

Due to extreme wear of the filter base plates and cleaning system, despite the applied glass flake coating, there were continuous dust emissions and the […]

Seven stainless steel chimneys including horizontal flue gas exhaust ducts in material grade 1.4571 were engineered for corrosion-resistant exhaust discharge. The design and choice of […]

For a client in the WTE sector with 7 incineration lines, each equipped with 2 ESP’s, we provide scheduled and ad-hoc maintenance on the ESP’s […]